'Digging Dirt' Session No. 2
|
Digger has done it's work!
The rough cut has now been completed by the
digger, leaving the basic bench cut ready for the second
task day for the Velocity Rough Riders. Now it was time
to get our hands dirty, and some back braking work was to
follow.
So on the 8th July eleven members met at the
new trail site at 9am to start the work. With shovels, loppers,
wheel barrow and lots of enthusiasm as we all set to work.
Levels and angles were marked out and the digging began.
The ground was compacted at an angle for water run off so
the trail could be sustainable, with hopefully minimum maintenance
for the future |
|
| |
After three hours
of steady earth moving, the park rangers brought up a welcome
cup of tea and coffee. We took this time to stand back and
admire our handy work. Next was the real test, Rough Riders
first bend. To make a bend sustainable the slopes has to
be correct to allow water run off so that erosion doesn’t
accure, this sounds easy but for first time trail builders
we had to get it right, and with the IMBA guide lines handy
I think we cracked it. By the time 2pm came we all called
it a day, so we could see our families and get a well earned
bath!
The section we worked on was nearly complete,
with minor works to be carried out. These minor works will
be completed during the evenings in the week, as the day
light is still on our side. The other sections will be worked
on, on Sundays, when the Velocity Rough Rider team can crack-on
and get this part of the trail passed off and opened ready
to be ridden, we then can move on to the next part of the
park.
Once again a big thanks to all helpers and a big pat on
the back to you all!
|
|
|
|
|
| |
| |
|